Business English >> Advanced Reading >> Project Implementation Review 2
Free Teacher Materials for
Business English
esl-lounge.com
Business English
esl-lounge.com
Advanced Reading
Project Implementation Review 2
Answers:
1. Staff turnover reached 38% during implementation 2. The Centre of Excellence was initially temporary 3. Local champions were originally seen as unnecessary 4. Legacy system complexity was underestimated 5. A three-month discovery period is now mandatory 6. 92% of requirements were ultimately met |
but evolved into a valuable permanent resource 2 despite significant human and financial costs 6 but saved $1.2 million in development costs 3 leading to $12.8 million in budget overruns 4 resulting in expensive contractor engagement 1 to prevent repeat system documentation issues 5 |