1. The primary cause of budget overrun appears to be:
Answer: b) inadequate initial assessment of existing systems
2. The document suggests that the company's approach to work-life balance during the project was:
Answer: b) fundamentally flawed given the turnover and exit interviews
3. The establishment of the Centre of Excellence demonstrates that:
Answer: c) unplanned outcomes can provide lasting value
4. The relationship between local champions and consultancy costs indicates that:
Answer: a) internal expertise development can offset external costs
5. Based on the recommendations section, the company's historical approach to system documentation was:
Answer: c) inconsistent and inadequate
6. The document's overall assessment of the project suggests it was:
Answer: b) technically successful but organisationally costly